Building Works and Notification
Notify Council before building work starts and apply for an occupation certificate when work is complete.
Before building work starts
Submit the Notice of commencement of building work [131.97 KB | PDF] at least two business days before work begins.
Complete and return the form listed in Attachments and resources, together with your Construction Certificate
Contact Building and Planning
Phone: 02 6023 8111
Email: info@alburycity.nsw.gov.au
As part of the Construction Certificate process, we’ll need to undertake inspections of building works at stages detailed in your certificate. To book an inspection, get in touch with us on 02 6023 8111. We’ll need at least 24 hour's notice so we can prepare for the inspection.
When building work is complete
Before a building can be occupied or used, you may need an Occupation Certificate confirming that the completed work is suitable for occupation, and/or use the structure.
Applications are submitted through the NSW Planning Portal. Upload all documents required by your construction certificate or complying development certificate.
Council will contact you to arrange a final inspection or request further information if required.
Note: all required documentation that is outlined in Attachment 1 of the Construction Certificate or Complying Development Certificate issued by us must be uploaded with your application.